Home

About

News

Services

Certification 

Careers

Affiliations

Contact us

43 Kirk Road, Carluke,              South Lanarkshire.                    ML8 5BN 

(  +44 (0)1555 771165
Ê  +44 (0)1555 771165

 

 

 

 
Recent Projects

Camster Wind Farm

           

 

Completion Date; June 2013             

No. of Turbines - 25 Mk7 Vestas

Termination Type: Pfisterer/Separable-T connectors.

 

C&J Dobbin have successfully completed the 33kV jointing and termination works at Camster Wind Farm, Watten, near Wick, Caithness.

The project consisted the cable jointing and termination works associated with the turbines, switchgear, ancillary distribution equipment, and final connection to the local REC's switchgear.

 


Wester Meathie Wind Farm

 

Completion Date; September 2012             

No. of Turbines - 2

Termination Type: Pfisterer/Separable-T connectors.

 

C&J Dobbin have successfully completed the medium voltage jointing and termination works at Wester Meathie Farm, Cupar, Forfar.

The project consisted the cable jointing and termination works associated with the turbines and final connection to the local REC's switchgear.

 


Spurness Wind Farm

       

 

Completion Date; September 2012             

No. of Turbines - 5

Termination Type: Pfisterer/Separable-T connectors.

 

C&J Dobbin have successfully completed the new 33kV jointing and termination works at Spurness  wind farm on Sanday island, within the Orkney islands.

The overall project consisted of the decommissioning and dismantling of three turbines, which were then replaced by five new turbines with a total nominal power of 10,000MW. The wind farm is estimated to produce 25 GW.h (for an equivalent of 2,500 hours of full load/year).

 


Gordonbush Wind Farm

        

 

Completion Date; March 2012             

No. of Turbines - 35

Termination Type: Pfisterer/Euromold

 

C&J Dobbin have successfully completed the 33kV jointing and termination works at Gordonbush windfarm near Brora in the Scottish highlands.

As part of our works we also completed the terminations associated with the LV power cabling and control wiring between the turbines and external HV/LV substations/isoblock units.

 

 


INEOS - Substation Replacement

 

Completion Date; Jan 2012             

C&J Dobbin successfully completed the H.V. Termination works on the substation/switchboard replacement project at INEOS, Grangemouth. The project included the terminations and jointing associated with the 11kV, 3.3kV, and 400V transformers and distribution system.

The project ran throughout 2011 and we were able to demonstrate our commitment to safety, quality, and tight programs. 

Our client was delighted with the works we carried out.


 

 

 

                                                     Beinn An Tuirc Wind Farm (Ext)

             

 

Completion Date; Feb 2011             

No. of Turbines - 19

Termination Type: Pfisterer/Euromold

 


INEOS - R7 Substation Replacement

 

Completion Date; Feb 2010             

C&J Dobbin successfully completed the H.V. Termination works on the R7 substation replacement project at INEOS, Grangemouth. The project included over 200 terminations associated with the 11kV, 3.3kV, and 400V distribution systems.

The project ran consistently over a ten month period and we were able to demonstrate our commitment to safety, quality, and tight programs. 

 


 

Little Cheyne Wind Farm

                     

 

Completion Date; Jan 2009             

No. of Turbines - 26

Termination Type: Pfisterer/Euromold

 


   Millennium Wind Farm Extension

           

Completion Date; September 2008             

No. of Turbines - 4

Termination Type: Euromold

 


Kilbraur Wind Farm

Completion Date; May 2008             

No. of Turbines - 19

Termination Type: Pfisterer/Euromold

 


                                                          Minsca Wind Farm

           

 

Completion Date; Feb 2008             

No. of Turbines - 16

Termination Type: Pfisterer/Euromold

 


                                                         Dalswinton Wind Farm

Completion Date; Jan 2008             

No. of Turbines - 15

Termination Type: Pfisterer/Euromold

 


Ben Aketil Wind Farm

          

C&J Dobbin have completed the High Voltage cable jointing and terminating works at the Ben Aketil wind farm on the Isle of Skye on behalf of Scottish Hydro Contracting. The project encompassed all 33kV terminating, jointing, and sheath repair works associated with ten Eurocon 2.5MW turbines, associated infrastructure, and main sub-station.

The project was a delight to work on as it was extremely well managed on and off site and we hope that we were able to demonstrate our experience, quality of workmanship, and general work ethos.


Edgar Allen - South Queensferry

Completion Date; Sept 2007

            C&J

C&J Dobbin were appointed directly by Edgar Allen to decommission fifteen 11kV/433V Distribution Transformers, Ring Main Units, and associated cabling from their new plant at South Queensferry. The project is well underway and involves all cable identification, cable spiking, PCB Analysis, removal of the units, and re-commissioning of the system in line with our clients requirements. C&J Dobbin have been able to meet and on occasions exceed our clients expectations to allow the tight program associated with demolition works to progress as intended.


Marks and Spencer - Princess St. - Edinburgh

Completion Date; Aug 2007

               

 

C&J Dobbin carried out all High Voltage Cable Jointing and Termination works, SAP HV Switching, and Pressure Testing as part of the refurbishment of the Princess St. M&S. The project consisted of a new 2 x 1000kVA packaged sub-station/switchboard and the associated HV switches. The final changeover to the new supply and switchgear involved a short duration shutdown that had to be managed to allow all frozen and refrigerated food equipment to remain energised whilst the final cable connections were being made. John Annan of Fletchers Retail said "C&J Dobbin did an excellent job, and made a very stressful weekend a lot easier". The project was a success and we look forward to providing our services on future projects with Fletchers and Twyver Switchgear.


INEOS - G4 Substation Refurbishment

Completion Date; June 2007

As part of our ongoing works with Watson Norie within INEOS' site at Grangemouth, we provided the High Voltage cable jointing and cable termination services for the refurbishment of the G4 sub-station. The project involved the installation of a new 3.3kV switchboard with all existing supply cables  being extended, re-routed, and re-terminated where necessary. In order to minimise production down time a series of intense short duration shut downs  were programmed to allow the Hazardous Area type jointing to be carried out. C&J Dobbin were able to meet the program to allow successful completion of the project.


Wharrels Hill Wind Farm

Completion Date; March 2007             

No. of Turbines - 8

Termination Type: Pfisterer/Euromold


High Pow Wind Farm

Completion Date; March 2007

No. of Turbines - 3

Termination Type: Pfisterer/Euromold


Earlesburn Wind Farm

Completion Date; February 2007

No. of Turbines - 15

Termination Type: Pfisterer/Euromold


Black Law Wind Farm  

Completion Date;  January 2006

No. of Turbines - 54

Termination Type: Pfisterer/Euromold

Initially we were appointed by Alfred McAlpine to carry out the 33kV cable termination and jointing works only, however our role was then extended to provide the Testing and Earth Sheath Fault location on the H.V. infrastructure cabling throughout the site.

Due to the terrain and below ground conditions where the H.V. cabling was run, several Earth Sheath faults had been present. Working closely with Alfred McAlpines site based staff, we were able to swiftly pinpoint all faults to allow us to rectify them with minimal disruption to the finished ground levels and avoid unnecessary delays.

Charles Dobbin said "It's a project that we are proud to be associated with as this wind farm is the largest on shore type in the UK to date. It is likely that this wind farm will be the flagship of Scottish Powers renewable scheme for some time to come. Black Law is the new benchmark as it has been completed with an amazing fifty-four turbines, which should make a significant contribution in assisting the UK meeting it's renewable energy targets".

For further details of the project please refer to the Scottish Government Website